Upcoming Work - Sewer Rehabilitation

Click for a pdf of the public notice

Anchor Construction will soon begin sewer rehabilitation work east of Connecticut Avenue along Klingle Road NW. This work will include the excavation, removal, and replacement of existing sewer line. Bypass pumping will be required during the replacement process; pumping will take place during daytime hours only.

Nearby residents may experience construction related noise between 7AM-7PM on Monday-Friday. In the event of inclement weather during the week, Saturday work may also be necessary.

Site preparation and excavation work will take place during the week of May 16; bypass pumping and pipe replacement will occur during the week of May 23. Sewer replacement is expected to be completed by May 27, 2016.