Klingle Watershed Green Streets Project - Public Meeting #2, June 13, 2016

The Klingle Watershed Green Streets project is hosting its second design phase public meeting on Monday, June 13th from 5:30-8:30 PM.  The meeting will be a walking tour of candidate sites, starting at the intersection of 36th Street and Lowell Street NW. Click here or on the images below for the full meeting flyer.

The Klingle Green Streets project team gave a initial project presentation at the KVT public meeting last November - click here for a link to the presentation.

 

 

Upcoming Work - Sewer Rehabilitation

Click for a pdf of the public notice

Anchor Construction will soon begin sewer rehabilitation work east of Connecticut Avenue along Klingle Road NW. This work will include the excavation, removal, and replacement of existing sewer line. Bypass pumping will be required during the replacement process; pumping will take place during daytime hours only.

Nearby residents may experience construction related noise between 7AM-7PM on Monday-Friday. In the event of inclement weather during the week, Saturday work may also be necessary.

Site preparation and excavation work will take place during the week of May 16; bypass pumping and pipe replacement will occur during the week of May 23. Sewer replacement is expected to be completed by May 27, 2016. 

Progress Update - May 10, 2016

Despite the seemingly endless rain, construction continues on the KVT project. With stream restoration complete, we've made the first production steps along the trail itself, starting with the underground work.

New storm water and drainage pipe will be installed throughout the trail.  Much like the gas line replacement, storm drain installation is challenging work, particularly with existing storm drains and utility lines running the full length of Klingle Road.

The first storm water pipe installation started last week, replacing a failed brick masonry culvert that outfalls into Klingle Creek. Scroll through the slideshow below to see the construction sequence.

Work within the Porter Street Interchange has been a key focus area over the past few weeks. Sidewalk installation along the Klingle Road to Porter Street Connector Ramp took place last week (Stage 2A in the graphic below).

Click through the slideshow below to see the sequence of construction along the connector ramp.

Over the past few weeks, the KVT contractor has also focused on constructing new wheelchair and bicycle ramps within the interchange, which are installed in accordance with DDOT and Americans with Disabilities Act standards.

Washington Gas is also progressing gas main replacement east towards Porter Street. Excavation and pipe replacement is now taking place within the active segment of Klingle Road, as seen in the left photo below.

Wildlife in Klingle Creek

Thanks to our stream restoration contractor Environmental Quality Resources this photo of Klingle Creek's newest residents.  We discussed in the December 30th progress update  that some of the trees removed for the new stream channel were reused to construct these root wad structures. This is a great example of the habitat that root structures provide within the creek. 

Photo Credit: Mike Dant, Environmental Quality Resources

Traffic Advisory - Ramp to Beach Drive Closure/Detour

DDOT Traffic Advisory Banner.jpg

FOR IMMEDIATE RELEASE

Media Contacts
Terry Owens — (202) 763-8635, terry.owens@dc.gov
Michelle Phipps-Evans — (202) 497-0124, michelle.phipps-evans@dc.gov

 

DDOT to Temporarily Close the ramp to Beach Drive, NW, from Klingle Road, NW, Beginning February 24

Lane closures in place while DDOT constructs the future Klingle Valley Trail

(Washington, DC) – The District Department of Transportation (DDOT) will close the ramp to Beach Drive, NW, from Klingle Road, NW, beginning on Wednesday, February 24, 2016 at 7 am, weather permitting. This closure is expected to remain until May 2016.

The ramp closure is needed for DDOT to safely construct the new Klingle Valley Trail along the ramp to Beach Drive, NW. The work includes water quality filtration systems, drainage pipe replacement, earthwork, curb and gutter replacement, paving, and guardrail installation.

Motorists who wish to access Beach Drive from Klingle Road should take the middle ramp up to Porter Street across to Beach Drive. A paved walking path will be maintained along the ramp to Beach Drive to allow pedestrian access to the Rock Creek Multi-Use Trail. Signage and protective barriers will also be used to maintain public safety.

Motorists should expect minor delays while using the detour to access Beach Drive from Klingle Road. Motorists, pedestrians and cyclists are urged to stay alert and to obey all construction signs.

###

 The mission of the District Department of Transportation (DDOT) is to enhance the quality of life for District residents and visitors by ensuring that people, goods, and information move efficiently and safely with minimal adverse impact on residents and the environment. Follow us on Twitter for transportation-related updates and more; like us on Facebook and visit the website at www.ddot.dc.gov. Visit goDCgo.com for more information on transportation options in the District.

Klingle Creek Post-Storm & Snow Melt - February 16, 2016

Today's rain storm/snow melt provided the second test in three weeks of the restored segments of Klingle Creek.  Even in their unfinished and un-vegetated states, the step pools, bank armoring, and flow controls are working well. Here are a few videos of the creek in action!

Starting in Segment 1, near Cortland Place:

Moving down to Segment 4, east of Connecticut Avenue:

Also within Segment 4, you can see the Riffle Grade Control and Log Structures described in previous construction updates functioning as designed to reduce flow velocity in the channel.

Progress Update - February 8, 2016

We've had a busy few weeks at the KVT project. Stream restoration work is nearing completion, and we are starting to prepare for the next phases of the project, to include roadway demolition, storm water and drainage construction, and trail construction.

It should come as no surprise to those in the DC area that the ever-changing weather has had a major impact on the project over the past three weeks.

First there was ice...

...then came the snow...

...which melted and was quickly washed away by the rain.

That said, the new stream features in Klingle Creek held up very well considering they are unfinished and not yet vegetated. The step pools and tailout areas easily handled heavy flow from both snow melt and rain, demonstrating both the added capacity and erosion protection that the stream restoration features provide.

With the remnants of the historic snow storm downstream, the restoration contractor was able to return to work in Klingle Creek. Recent work includes step pool, stone toe (stream bank armoring), and fabric encapsulated soil lift construction.

The contractor also completed a riffle grade control feature, which mimics the naturally-occurring flat areas in streams where the water flows over a mix of river rock and small boulders.

The contractor also started work on clay channel blocks, which span the width of the stream channel and extend 4-5 feet into the earth.  Clay is the most dense of all naturally-occurring soil materials, and when well compacted it forms a water tight barrier. The groundwater level in the upper reach of Klingle Creek is high, and these clay blocks will reduce the amount of groundwater that bypasses the stream channel.

A DDOT inspector tests the density of the compacted clay in the channel block.

Meanwhile, the new retaining wall across from the Woodley Park Towers is nearing completion.  The salvaged stone finish is taking shape!

 A mason applies mortar between salvaged stones.


Progress Update - Week Ending December 11, 2015

Stream restoration work has been the priority activity on the project for the past two weeks, with the stream restoration contractor, Environmental Quality Resources, focusing on Segment 4 east of Connecticut Avenue.

Stream restoration work for the past two weeks focused on Segment 4, east of Connecticut Ave.

The contractor started Segment 4 work by establishing the new stream banks. This was achieved by excavating the existing banks and installing large stones cut roughly into blocks.  The blocks (called "imbricated riprap") are stacked in such a way to armor the stream bank and greatly reduce erosion.

On the opposite bank, EQR started installation of fabric encapsulated soil lifts.  These soil lifts will be vegetated and will absorb overflow during flood events when complete.

Once the stream banks are built up, the contractor will then install step pools within the stream.  Step pools greatly reduce stream flow and erosion by temporarily pooling water before it cascades to the next lower pool. Segment 4 will have 15 step pools when complete.  EQR installed the first step pool boulder cluster last week.  Boulders for step pool clusters are carefully selected to ensure a watertight fit.

The westernmost step pool boulder cluster in Segment 4 was set last week.

Overhead schematic of a step pool.

Finally, the contractor removed two Ash trees along Klingle Road that will soon succumb to the Emerald Ash Borer (EAB) epidemic. Given the trees' size and position hanging over Klingle Road, the trees had to be removed for safety purposes. Click here for more information from DDOT regarding Ash trees and the EAB.

 Crews remove an Ash tree along Klingle Road.

Crews remove an Ash tree along Klingle Road.

Progress Update - Week Ending November 27, 2015

It's been a busy couple of weeks on the Klingle Valley Trail! Stream restoration and retaining wall construction are underway, gas line relocation work continues, and the east entrance to the jobsite is now open for construction traffic.

After two weeks of site preparation and materials deliveries, the stream restoration contractor started work on Segments 2 and 3, shown on the image below. 

KVT stream restoration segments.

Stream restoration construction is difficult work.  The contractor has to dam up the upstream side of the creek and divert the water flow using a pump and hose system. Once the work area is sufficiently dry, the contractor then excavates the stream bed to provide a stable foundation for the restoration features.  In this case, the contractor installed a Stone Toe, which consists of stacked boulders that will prevent future erosion along the stream banks. The stones come from the quarry roughly cut into block shape (called "imbricated riprap"), and must be placed at precise locations and elevations based on the design stream channel levels. 

Additional stream restoration site preparation activities took place last week, including access point grading and tree removals. Some of the trees that were removed to accommodate the new stream channel were saved with root wads in tact to be reused in the restored stream. The root structure when placed in the stream creates new habitat for aquatic life. 

The prime contractor started work on the first new retaining wall on the project. The wall is near the west end of the trail just behind the Woodley Park Towers building. The wall replaces a stone masonry wall that collapsed many years ago. The wall will serve as one of the banks of Klingle Creek, so the contractor had to take similar steps to dewater the area each day using pumps. With all pump-around activity on the project, the pumps must be turned off by 7 PM to minimize noise disturbance.

The concrete foundation for the retaining wall was installed on Monday, November 23rd. 

To maintain the historic character of Klingle Road, the project will reuse much of the existing stone from the area. For the retaining wall, we are salvaging stone from the existing stone walls that collapsed into the creek. 

The contractor also stabilized the east entrance of the job site, near the Porter Street interchange.  The east entrance is now accessible to construction traffic and will prevent any backups at the west entrance, where Washington Gas continues to work along both Klingle Road and Cortland Place. Look for a new retaining wall to be built along this slope in 2016.

Washington Gas continues its work on the west end of the project. Phase 1 is nearly complete, with 300 feet of pipe left to be installed, and Phase 4 continues along Cortland Place towards Devonshire Place.