Progress Update - February 8, 2016

We've had a busy few weeks at the KVT project. Stream restoration work is nearing completion, and we are starting to prepare for the next phases of the project, to include roadway demolition, storm water and drainage construction, and trail construction.

It should come as no surprise to those in the DC area that the ever-changing weather has had a major impact on the project over the past three weeks.

First there was ice...

...then came the snow...

...which melted and was quickly washed away by the rain.

That said, the new stream features in Klingle Creek held up very well considering they are unfinished and not yet vegetated. The step pools and tailout areas easily handled heavy flow from both snow melt and rain, demonstrating both the added capacity and erosion protection that the stream restoration features provide.

With the remnants of the historic snow storm downstream, the restoration contractor was able to return to work in Klingle Creek. Recent work includes step pool, stone toe (stream bank armoring), and fabric encapsulated soil lift construction.

The contractor also completed a riffle grade control feature, which mimics the naturally-occurring flat areas in streams where the water flows over a mix of river rock and small boulders.

The contractor also started work on clay channel blocks, which span the width of the stream channel and extend 4-5 feet into the earth.  Clay is the most dense of all naturally-occurring soil materials, and when well compacted it forms a water tight barrier. The groundwater level in the upper reach of Klingle Creek is high, and these clay blocks will reduce the amount of groundwater that bypasses the stream channel.

A DDOT inspector tests the density of the compacted clay in the channel block.

Meanwhile, the new retaining wall across from the Woodley Park Towers is nearing completion.  The salvaged stone finish is taking shape!

 A mason applies mortar between salvaged stones.


Progress Update - Week Ending November 27, 2015

It's been a busy couple of weeks on the Klingle Valley Trail! Stream restoration and retaining wall construction are underway, gas line relocation work continues, and the east entrance to the jobsite is now open for construction traffic.

After two weeks of site preparation and materials deliveries, the stream restoration contractor started work on Segments 2 and 3, shown on the image below. 

KVT stream restoration segments.

Stream restoration construction is difficult work.  The contractor has to dam up the upstream side of the creek and divert the water flow using a pump and hose system. Once the work area is sufficiently dry, the contractor then excavates the stream bed to provide a stable foundation for the restoration features.  In this case, the contractor installed a Stone Toe, which consists of stacked boulders that will prevent future erosion along the stream banks. The stones come from the quarry roughly cut into block shape (called "imbricated riprap"), and must be placed at precise locations and elevations based on the design stream channel levels. 

Additional stream restoration site preparation activities took place last week, including access point grading and tree removals. Some of the trees that were removed to accommodate the new stream channel were saved with root wads in tact to be reused in the restored stream. The root structure when placed in the stream creates new habitat for aquatic life. 

The prime contractor started work on the first new retaining wall on the project. The wall is near the west end of the trail just behind the Woodley Park Towers building. The wall replaces a stone masonry wall that collapsed many years ago. The wall will serve as one of the banks of Klingle Creek, so the contractor had to take similar steps to dewater the area each day using pumps. With all pump-around activity on the project, the pumps must be turned off by 7 PM to minimize noise disturbance.

The concrete foundation for the retaining wall was installed on Monday, November 23rd. 

To maintain the historic character of Klingle Road, the project will reuse much of the existing stone from the area. For the retaining wall, we are salvaging stone from the existing stone walls that collapsed into the creek. 

The contractor also stabilized the east entrance of the job site, near the Porter Street interchange.  The east entrance is now accessible to construction traffic and will prevent any backups at the west entrance, where Washington Gas continues to work along both Klingle Road and Cortland Place. Look for a new retaining wall to be built along this slope in 2016.

Washington Gas continues its work on the west end of the project. Phase 1 is nearly complete, with 300 feet of pipe left to be installed, and Phase 4 continues along Cortland Place towards Devonshire Place.